Viewing 10 posts - 1 through 10 (of 10 total)
  • Author
    Posts
  • #1435501

    I am using the Event Calendar (basic) that is included with Enfold. Up until January 1, 2024 it was working perfectly. However, now when I import new events via CSV, all dates are set to January 1, 1970. I cannot find an Event Calendar forum to ask this question in, so any help would be appreciated. If you can point me to the proper forum, that would be very much appreciated too.

    #1435526

    Hey GUMC-Rosier,

    Thank you for the inquiry.

    Can you reproduce the issue when using a different theme? Please clone the site to a staging environment, then provide the CSV file so that we can check the issue further.

    Best regards,
    Ismael

    #1435924

    Hi Ismael,
    I have created a clone with UpdraftPlus and have included the information below.
    Here are the steps I took in reproducing the problem:
    Using Enfold/child theme
    Saved from my calendar as an .xls file
    Edited and converted to a .csv file containing 12 events from April 1 – 3, 2024
    Only included fields event name, start date, end date, start time, end time, venue
    Dates in csv show as m/d/yyyy (4/1/2024)
    Uploaded, preview shows correct dates
    All events uploaded with the start and end dated of January 1, 1970
    Took 15+ minutes

    Imported from CSV-file-for-example.csv
    Include all fields
    10 events, dates ranging from June 16 – September 1, 2022
    Dates show as d-m-yyyy in csv
    Dates show as yyyy-mm-dd in preview
    Preview shows correct date
    All events uploaded with start date of January 1, 1970, and correct end date (2022)
    Took less than a minute

    Moved all of the above events to trash
    Switched to Enfold (not child theme)
    Same results as above

    Moved all of the above events to trash
    Switched to Twenty-Twentyfour theme
    Same results as above

    I would say that something is wrong with the way I’ve formatted my csv file. But the file, downloaded directly from The Event Calendar website, does the same thing.

    I even went so far as to download a fresh copy, did not open or edit it, and tried importing those events. And the same thing happened again.

    I have the csv file from the last successful upload. I moved the 5 most recent events to trash. However, it showed 1 event in trash and 4 events in “ignored.” I permanently deleted those 5 events, and then tried importing from the last successful csv file. They imported instantly and correctly, BUT, it created two identical entries for each event.

    Any help you can provide would be very much appreciated. Hopefully it’s some stupid little thing, but for the life of me, I can’t figure out what.

    Kathy R.

    #1435960

    Hi,

    Thank you for the inquiry.

    Importing the sample csv file (CSV-file-for-example) seems to be working as expected. It accurately saves the start and end dates as expected. However, importing the other file is taking quite a while.

    We noticed that there are a lot of missing fields or columns in your own CSV file compared to the sample CSV file provided by the plugin. You may need to copy the exact format of the sample CSV file, including the order of the columns, to make sure that the importer can read the data properly.

    Best regards,
    Ismael

    #1436011

    Thank you!!! That worked perfectly. I thought it must be something simple since I couldn’t find any other posts about it. It’s great to have a second pair of eyes looking at it. I really appreciate your quick response.
    Kathy R.

    • This reply was modified 8 months, 4 weeks ago by GUMC-Rosier.
    #1436030

    Hi,

    Thanks for the update. Please let us know if you should need any further help on the topic, or if we can close it.

    Best regards,
    Rikard

    #1436283

    I usually import the calendar once a month. The real test will be to see if everything works when i update at the end of March.

    Kathy R.

    #1436293

    Hi,
    OK, we will leave this open until you can check again, if it is successfully again please let us know so we can close this thread.

    Best regards,
    Mike

    #1439608

    I just imported the next two months to my Event Calendar, using all the column headings in the CSV file. Everything seems to have worked perfectly. Thank you for your help!
    Kathy R.

    #1439615

    Hi,
    Glad to hear that you have this sorted out, if you have any further questions please create a new thread and we will gladly try to help you. Thank you for using Enfold.

    Best regards,
    Mike

Viewing 10 posts - 1 through 10 (of 10 total)
  • The topic ‘Event Calendar imports all 1970’ is closed to new replies.